Construction Update for March 25, 2022

posted in: Construction Updates | 0

In this issue:

  • Water main replacement on Chanate Road continues
  • Sewer laterals on Strawberry Drive to be completed next week
  • Updated overall project schedule

NOTE All schedules are subject to change due to weather or other circumstances

Water main replacement on Chanate Road continues
Progress is being made on the water main replacement on Chanate Road between Terra Linda Drive and Belvedere Way. Current work includes installing main line extensions, hydrant connections, and water service line connections, which will continue into mid-to-late-April. Motorists should expect daytime traffic control and minor delays.

Sewer laterals on Strawberry Drive to be completed next week
The main pipeline work is complete, and installation of sewer laterals on Strawberry Drive is underway. This work is expected to be completed by the end of next week. Please watch for crews and equipment.

Updated overall project schedule
The two-year Chanate Sewer Replacement Project is on schedule for completion in summer of 2022. Below is an updated summary of the primary work elements still to be accomplished. As the project moves forward motorists should watch for work crews, equipment, and periodic temporary traffic control. Motorists may experience short delays. Trenches will be plated and roadways fully reopened to traffic at the end of each work day and on weekends.

All schedules are subject to change due to weather or other circumstances

  • Replace water main on Chanate Road between Terra Linda Drive and Belvedere Way – underway
  • Install sewer pipelines on:
    • Strawberry Drive – underway
    • Mendocino Avenue (primarily night work, +/-500 feet heading north from Chanate Road) – anticipated to occur in mid-April; dependent on other work being completed first
    • Lomitas Lane – anticipated to occur in mid-to-late April; dependent on other work being completed first

We’ll update you with specific dates for the Mendocino Avenue and Lomitas Lane work elements as the schedule is finalized.

  • Repave/resurface roadways which were disrupted during construction – anticipated to begin late April 2022, continuing for approximately one month (final timing dependent on weather and completion of other work)
  • Abandon the old sewer pipeline (filling with concrete) – expected to take place mid-June through mid-July 2022 (start date regulated by California Department of Fish and Wildlife)

Please exercise additional caution when traveling on Chanate Road and other streets where work is taking place. Watch for crews and equipment, be aware of signage, flaggers, and lane changes. Observe posted speed limits, and never drive faster than is safe for the conditions.