Construction Update for July 22, 2022

posted in: Construction Updates | 0

In this issue:

  • Final work remaining

NOTE All schedules are subject to change due to weather or other circumstances

Final work remaining
Work is expected to be substantially complete by the end of July, with some minor extending into the first week of August.

  • Crews are continuing the final stages in the process of abandoning the old sewer pipelines (filling the old pipes with concrete) and other finalizing and clean-up work. This will continue through July 29.
  • Final roadwork/drainage finishing items on Strawberry Drive, and replacement of damaged approaches to the Andy Way/Baldwin Way emergency vehicle access point are now scheduled for the week of August 1 (note: the bollards at Andy Way/Baldwin Way will remain in place during this work, and thereafter except as directed by emergency/public safety staff).
  • Also the week of August 1, any “punch list” items, which are the final details and clean-up work, will be addressed.

During these final few weeks of work, please continue to watch for crews, traffic control, and equipment throughout the project area.