Construction Update for August 12, 2022

posted in: Construction Updates | 0

In this issue:

  • Final work remaining

NOTE All schedules are subject to change due to weather or other circumstances

Final work remaining

  • Any remaining “punch list” items, (final details and clean-up work) and de-mobilization of the contractor’s equipment will take place next week (week of August 15), with the exception of final striping in the parking lot at 2604 Mendocino Avenue, which will take place on August 22.

During these last days of work, please continue to watch for crews, traffic control, and equipment throughout the project area.