Construction Update for May 20, 2022

posted in: Construction Updates | 0

5/20/2022: Lomitas Ln resurfacing rescheduled for May 23 – June 3; Sunday work in parking lot at 2602 Mendocino Ave; Chanate Rd water main expected to be complete by May 27; Resurfacing coming to streets throughout the project area; Updated overall project schedule

Construction Update for May 13, 2022

posted in: Construction Updates | 0

5/13/2022: Road resurfacing to start in mid-May; Lomitas Ln pipeline installation continuing; Sunday work in parking lot at 2602 Mendocino Ave; Chanate Rd water main testing/tie-ins continuing into late May; Updated overall project schedule

Construction Update for April 15, 2022

posted in: Construction Updates | 0

4/15/2022: Lomitas Ln pipeline installation RESCHEDULED to start April 20; Mendocino Ave night work starting April 18; Chanate Rd water main replacement testing and tie-ins continuing into mid-May; Updated overall project schedule

Construction Update for April 8, 2022

posted in: Construction Updates | 0

4/8/2022: Lomitas Ln pipeline installation scheduled to start April 14; Mendocino Ave night work scheduled to start April 17; Chanate Rd water main replacement testing and tie-ins continuing into early May; Updated overall project schedule