Construction Update for April 15, 2022

posted in: Construction Updates | 0

4/15/2022: Lomitas Ln pipeline installation RESCHEDULED to start April 20; Mendocino Ave night work starting April 18; Chanate Rd water main replacement testing and tie-ins continuing into mid-May; Updated overall project schedule

Construction Update for April 8, 2022

posted in: Construction Updates | 0

4/8/2022: Lomitas Ln pipeline installation scheduled to start April 14; Mendocino Ave night work scheduled to start April 17; Chanate Rd water main replacement testing and tie-ins continuing into early May; Updated overall project schedule